Travel shifts coming to US 12/SR 8
June 7, 2024 8:30AM PDT
A lane shift is coming today on Highway 12, with more work coming next week to Grays Harbor.
Travelers who use US 12 and State Route 8 between Montesano and the Thurston County line will see changes to the roadway over the next week.
What to expect
7 a.m. to 3 p.m. Friday, June 7:
- Crews will shift one westbound lane over the median to the eastbound side of US 12.
- Work zone is located near Schouweiler Road west of Elma.
7 a.m. to 3 p.m. Wednesday, June 12:
- Crews will shift one eastbound lane onto a new SR 8 bridge.
- Work zone is located near Heise Road between Elma and McCleary.
7 a.m. to 3 p.m. Friday, June 14:
- Crews will shift one westbound lane over the median to the eastbound side of SR 8.
- Work zone is located near Mox Chehalis Road east of McCleary.
Travelers will see a rolling slowdown during each traffic shift.
This work is weather-dependent and subject to change. Real-time travel information is available on the WSDOT app and statewide travel map.
This work is part of a series of traffic shifts happening this spring and summer for fish habitat work under US 12 and SR 8.