Culvert projects prioritized by Gov. Inslee
More culvert replacement projects could be coming to our area, and they could be coming sooner than expected.
Governor Jay Inslee this week ordered the Washington State Department of Transportation to begin the immediate ramp-up of culvert repairs around the state, saying that it is an urgent and crucial priority for improving fish passage and salmon recovery.
According to a release, state officials estimate there are approximately 2,000 culverts statewide, however, nearly half of them are too small or too damaged and actually impede the ability of salmon and other fish to reach their spawning ground.
In 2001, the U.S. government sued Washington state on behalf of 21 Northwest tribes saying the state is depriving tribes of their fishing rights by failing to ensure adequate fish passage.
A U.S. district court ruled in favor of the tribes in 2013 and ordered the state to replace those 1,000 culverts, and set a deadline of 2030 for about 490 of the highest priority barriers.
The U.S. Supreme Court upheld that decision last year. WSDOT estimates it will cost about $3.7 billion to fully meet the court’s order.
Since the original lawsuit, a number of local culverts have been replaced. Mot notably the projects include those on Highway 12 outside McCleary and Montesano.
Gov. Inslee had proposed a plan in December that established a dedicated funding source that would provide $275 million in the 2019-21 biennium and $700 million per biennium starting in 2021. The funding would allow WSDOT to more than double its current pace of culvert repairs. In addition to meeting the court’s order, the culvert repairs are part of the governor’s plan to increase Chinook salmon prey for Southern Resident orcas.
Legislators decreased that funding proposal from $108.5 million in 2017-19 to $100 million in 2019-21.
As he completed signing the new 2019-21 state transportation budget Tuesday, Inslee voiced significant frustration with legislators and issued the following statement: